April 2008 |
|
| |
External plastering works are ongoing in Preti Court T8 and 9 and internally, plastering is complete in T9F and half-completed in T8F. |
| › |
January 2008 |
|
| |
Works to Caravaggio Court T4 & T5 are all complete. Practically all the contracts in this cluster have now been signed. Works are progressing on the Belvedere structure which will link the foreshore walkway with the piazza. |
| › |
May 2007 |
|
| |
The first apartments in the front blocks |
| › |
March 2007 |
|
| |
These blocks are now complete, certification letters have been issued and first tenants have now taken up residence. |
| › |
September 2006 |
|
| |
Works in progress on site: T4 and T5 Blocks |
| › |
May 2006 |
|
| |
The two high-rise blocks in this first complex (Caravaggio Court) are now nearing completion |
| › |
February 2006 |
|
| |
T4B Exterior rendering is now almost complete and all mechanical and electrical works within the apartments are finalised. |
| › |
November 2005 |
|
| |
The civil works in these apartments are now all complete whilst snagging is being finalised. |
| › |
August 2005 |
|
| |
Whilst the civil works are complete, the snagging work is now almost finalised as well. The exterior plastering of the front blocks has commenced and progressing rapidly. |
| › |
June 2005 |
|
| |
Works to the superstructure in T4 and T5 front and back blocks are now complete and last snagging works are being finalised... |
| › |
May 2005 |
|
| |
Works to the superstructure in T4 and T5 front and back blocks are now complete and last snagging works are being finalised. In the meantime mechanical and electrical services works for the common areas of the blocks continues with lifts being installed in block 4B. Mechanical and electrical services within the apartments are just about to commence after receipt of the final submissions of apartment m & e layouts. |
| › |
March 2005 |
|
| |
Works to the superstructure in the T4 and T5 front and back blocks are now complete, and final snagging works are in hand. |
| › |
January 2005 |
|
| |
Works to the superstructure in the front blocks T4F and T5F are complete... |
| › |
November 2004 |
|
| |
The works to the superstructure in T4F are now complete. In T5F works to the... |
| › |
August 2004 |
|
| |
Shell and core works of T4F are practically complete. In T5F the... |
| › |
June 2004 |
|
| |
Works in Block T 4B are progressing well and the 4th floor apartments are well underway... |
| › |
May 2004 |
|
| |
In block T6F and the two back blocks, the first ground floor apartments are being roofed over… |
| › |
March 2004 |
|
| |
Shell and core works on block T4 Foreshore are nearing completion… |
| › |
January 2004 |
|
| |
The ground floor level of T4F is now complete in shell and the first floor is nearing structural completion… |
| |