Tigné Point: Latest Progress

 
  External plastering works are ongoing in Preti Court T8 and 9 and internally, plastering is complete in T9F and half-completed in T8F.
  Works to Caravaggio Court T4 & T5 are all complete. Practically all the contracts in this cluster have now been signed. Works are progressing on the Belvedere structure which will link the foreshore walkway with the piazza.
  The first apartments in the front blocks
  These blocks are now complete, certification letters have been issued and first tenants have now taken up residence.
  Works in progress on site: T4 and T5 Blocks
  The two high-rise blocks in this first complex (Caravaggio Court) are now nearing completion
  T4B Exterior rendering is now almost complete and all mechanical and electrical works within the apartments are finalised.
  The civil works in these apartments are now all complete whilst snagging is being finalised.
  Whilst the civil works are complete, the snagging work is now almost finalised as well. The exterior plastering of the front blocks has commenced and progressing rapidly.
  Works to the superstructure in T4 and T5 front and back blocks are now complete and last snagging works are being finalised...
  Works to the superstructure in T4 and T5 front and back blocks are now complete and last snagging works are being finalised. In the meantime mechanical and electrical services works for the common areas of the blocks continues with lifts being installed in block 4B. Mechanical and electrical services within the apartments are just about to commence after receipt of the final submissions of apartment m & e layouts.
  Works to the superstructure in the T4 and T5 front and back blocks are now complete, and final snagging works are in hand.
  Works to the superstructure in the front blocks T4F and T5F are complete...
  The works to the superstructure in T4F are now complete. In T5F works to the...
  Shell and core works of T4F are practically complete. In T5F the...
  Works in Block T 4B are progressing well and the 4th floor apartments are well underway...
  In block T6F and the two back blocks, the first ground floor apartments are being roofed over…
  Shell and core works on block T4 Foreshore are nearing completion…
  The ground floor level of T4F is now complete in shell and the first floor is nearing structural completion…
 
 
   
 
   
 
   
 